Archive of entries posted on July 2010

Union Station Update #22

The newly enhanced dewatering system was approved and fired up while I was away.  It is fully functional and work on the project has resumed with amazing progress in a short time.   I will report more on the dewatering system in a day or two.

In the photo below, you can see that construction of the bus terminal structure is underway.  At a pace of 300 cubic yards per day, a six-inch thick mud slab is being poured.  It provides a solid surface upon which the Kiewit crew can work.  A water-proof membrane will be installed over the mud slab, and a three- to four-foot thick  concrete foundation (aka floor of the bus terminal) will be poured on top of the membrane.  The thickness of the floor varies depending on the location.  The membrane will prevent the need to pump ground water after the project is complete.

Also notice in the photo the foundations for two escalators and one elevator.  As I previously mentioned, the other three holes (the ones with upright sheet pile) are for under-floor utilities.  The crane has taken its place on the stone track on the left side of the hole, as seen at the top of the photo.  Since I took this photo yesterday, workers have started installing concrete forms along the right side of the mud slab.  The forms appear to be about four feet high and will be the outer edges of the bus terminal floor.

Here’s a closer, but still too distant, shot of work on the mud slab.  Notice the machine at the bottom center of the photo.  It uses the same GPS technology that the bulldozer used to ensure exact elevations.

Work continues on the light rail tracks and station.  In the upper right corner of the photo below, you can see an additional foundation that was poured since my last update.

There is no observable progress from the outside of the temporary Amtrak terminal other than the new traffic light that is being installed (see below) at the corner of 21st and Wewatta streets.  It will enable Amtrak passengers to stop traffic as they walk from the terminal to the temporary loading platform across Wewatta Street.  Inside the terminal, DRG Construction workers are installing drywall and utilities.

Thank you to Hunter Sydnor and Joy Wasendorf of Kiewit for providing most of the information in today’s update.

Finally, there have been reports of a sly worker showing up after nearly everyone else has left the job site at the end of the day.  Last evening, I finally got a photo of him or her as you can see to the right of and below the cone in this photo.  He or she has a very close resemblance to a fox.  (Sorry about the resolution that was lost in the cropping process.)  It’s good to know that there is a sharp eye on the project after the workday.

One more thing.  I uploaded 16 more photos this week to our Denver Union Station page at JobSiteVistor.com.


DenverInfill Blog Turns Five!

It was five years ago today, July 5, 2005, that the DenverInfill Blog made its debut.

A bit of history: I started working on the DenverInfill website in the spring of 2004. It took me a little over a year to complete all of the various downtown and center city district pages and the other major sections of the website. It was early July 2005 when I found myself with a finished website but with one of the ten menu tabs at the top still unused. Hmmm… what to do? Then it hit me: “What about a blog!” So on July 5, I named the final unused tab at the top the “DenverInfill Blog” and wrote my first post about rumors of a new condo tower called One Lincoln Park planned for somewhere along Lincoln Street. Back then I didn’t use any blogging software but wrote the posts on static webpages. You can access those original entries here. I did that for about a year before switching to the Blogger format on August 1, 2006. On December 20, 2009, the new (current) WordPress version of the DenverInfill Blog was launched, which was also the beginning of a new era for DenverInfill focusing on urbanism and not just infill.

The most popular DenverInfill Blog post? It’s not even close. On September 1, 2006, I wrote a silly piece called Guide to Suburban Denver Subdivision Names.  That day I had about 500 visits to the blog, which was about average at the time. Then on October 9, over a month later, my post on subdivision names got picked up by Curbed LA and then the next day by Boing Boing and my site traffic went through the roof with more than 10,000 visits over a three-day period. Since then, Guide to Suburban Denver Subdivision Names has thrived in cyberspace and continues to be viewed about 600 times every month, almost four years later. Overall, DenverInfill is viewed about about 60,000 times a month on average.

The most commented on DenverInfill Blog post? That would also be the briefest DenverInfill Blog post ever, at just eight words in length. Sixty-three people had something to say about The Shortest Path.

Over the next five years, the DenverInfill Blog will continue to evolve, but our mission will remain the same:

  • To inspire Denver citizens to envision and strive for exceptional urbanism in their city and region
  • To inform and educate on topics relating to urban planning and city-building
  • To serve as an online resource of notable urban projects, plans, policies, and programs throughout Denver
  • To promote and showcase Denver and its opportunities to the world
  • To advocate for positive changes to Denver’s existing and future built environment

To conclude, a big THANK YOU to all of you out there who visit this blog on a regular basis and for your kind words of support, and to the DenverInfill Blog contributors who are helping me expand the discussion about urbanism in Denver.

This is DenverInfill Blog post #884. Cheers!


FasTracks Overview and Update

Obviously transit is playing a larger and larger role in the metro area, so I think it’s only fitting that my very first transit post is an overview and status update of one of the largest transit expansion programs in the country. I’m sure most of us know the basics, but hopefully there’s some tidbits in here that’ll be new info.

RTD FasTracks is metro Denver’s $6.5 billion regional transportation expansion program made up of nine rapid transit corridors, 31 new park-n-Rides, the redevelopment and reconfiguration of Denver Union Station (DUS) into a truly multimodal transit-oriented development, and the enhancement of the bus network and transit hubs across RTD’s district. The FasTracks program will include 122 miles of new light rail and commuter rail, 18 miles of bus rapid transit (BRT), 21,000 new parking spaces at rail and bus stations and enhanced bus service across the District. See the map below for an idea as to FasTracks’ reach.

2010-07-02_FasTracks1

FasTracks is made up of several different components. The following transit corridors make up the RTD FasTracks program:

West Corridor – $700 million light rail line connecting Downtown Denver and the Jefferson County Government Center along a new 12.1-mile corridor. The project runs along an old railroad right-of-way acquired by RTD and also serves west Denver, Lakewood, the Denver Federal Center, and Red Rocks Community College at 12 stations.

East Corridor – $1.2 billion commuter rail line connecting Downtown Denver and DIA along a new 22.8-mile corridor. The new rail line will serve east Denver and Aurora on its way to DIA. This project is part of the Eagle P3 project, one of the first transit projects to utilize a public-private partnership (PPP) in the country. (Info on the P3 project is coming in a future blog post)

Gold Line – $517 million commuter rail line connecting Downtown Denver, Adams County, Wheat Ridge, and Arvada along a new 11.2-mile corridor. The project will also be part of the Eagle P3 project.

Northwest Rail – $665 million commuter rail line connecting Downtown Denver, Adams County, Westminster, Broomfield, Louisville, Boulder, and Longmont along a new 41-mile corridor. The commuter rail will run along the same tracks as frequent freight rail service. An initial segment from DUS to 71st and Lowell will be completed as part of the P3 project.

North Metro - $910 million commuter rail line connecting Downtown Denver, Adams County, Commerce City, Northglenn, and Thornton along a new 18-mile transit corridor. The right-of-way for the majority of this corridor has already been acquired by RTD.

I-225 Corridor – $626 million light rail line traveling along I-225 through Aurora from the existing Nine Mile Station north 10.5 miles to the future Peoria/Smith Station along Aurora’s western border with Denver. The corridor will service Aurora’s Municipal Building, the Aurora Town Center, as well as the Anschutz Medical Campus (formerly the Fitzsimons Army Medical Center).

Southeast Corridor Extension - $159 million, 2.3-mile extension of the Southeast Corridor which opened in 2006. The extension will serve Lone Tree’s future downtown, as well as the Sky Ridge Medical Center.

Southwest Corridor Extension - $156 million, 2.5-mile extension of the Southwest Corridor which opened in 2000. The extension will travel south along Santa Fe Drive, through a reconfigured and reconstructed C-470/Santa Fe Drive interchange, and serve Highlands Ranch at a new park-n-Ride at Lucent Blvd. and C-470.

Central Corridor Extension – $65.5 million, 1-mile extension of the Central Corridor which opened in 1994. The extension will travel north along Downing Street and end at 38th and Blake Streets, connecting the Central Corridor with the East Corridor.

US 36 BRT - $23.3 million (Phase 1) project to enhance transit service along the US 36 Corridor between Denver and Boulder. Phase 1 projects included expanded park-n-Rides, pedestrian bridge construction, and installation of slip ramps along the highway. Phase 2 is dependent on CDOT action along the highway.

Since the FasTracks vote in 2004, the program has encountered a number of challenges that are outside of RTD’s control (or anyone’s control for that matter) –  namely an increase in the cost of construction materials (concrete, steel, and copper) and a significant decrease in sales tax revenues. Due to these economic challenges, it will require additional revenues from what was originally planned to complete FasTracks in the timeframe promised in 2004. FasTracks is facing a $2.45 billion budget gap brought on by a combination of rising commodity prices and declining sales tax revenues, which are the backbone of its funding mechanism. If RTD does decide to pursue a new sales tax increase, it would take an additional 0.4% (on top of the original 0.4% for FasTracks and 0.6% for general RTD operations) to fill the funding gap. Any new tax would include a sunset provision.

To deliver the program within the next 10 years or so, RTD will need to solve the gap between the project cost and the available revenue brought in by sales tax and other sources. Despite of the budgetary challenge, RTD says they’re committed to delivering the program by 2019. In spite of the challenges brought on by unforeseen economic forces, RTD has been able to initiate construction on several major components of the FasTracks program. The West Corridor broke ground in 2008 with major construction commencing in 2009 and will open for revenue service in early 2013.

I know Rick’s got it covered, but as we all know, DUS broke ground on major reconfiguration and redevelopment activity in March, following a loan package from the Federal Railroad Administration (FRA), Federal Transit Administration (FTA), and United States Department of Transportation (DOT). The entire $500 million reconfiguration is expected to be complete and open for service in 2015.

The RTD Board of Directors selected Denver Transit Partners (DTP) in June as their P3 Concessionaire to deliver commuter rail service to DIA along the East Corridor, Arvada and Wheat Ridge along the Gold Line, Westminster along Northwest Rail, and a new commuter rail maintenance facility. Groundbreaking for the East Corridor is expected sometime in August, with groundbreaking of other P3 components later next year.

By the end of 2010, 47 miles of new FasTracks rail lines will be either under construction or under contract. This will more than double RTD’s existing rail system (currently in operation or under construction) from 35 miles to about 82 miles. By mid-2011, five of the 11 FasTracks projects will be under construction – West Corridor (groundbreaking in 2008), Denver Union Station (2010), East Corridor (2010), Gold Line (2011), and Northwest Rail Electrified Segment to 71st and Lowell (2011).

It’s a HUGE project with HUGE potential to really transform how metro Denver moves. It’s great to see the progress that we’re already seeing – every new project is a big step in the right direction. Let’s hope that the complicated budget situation is resolved soon so they can get these trains running!