Skip to content
Archive of posts filed under the Union Station category.

DaVita HQ Update #5

The DaVita Headquarters building is beginning to make its full presence in the area. The crane has been taken down, the facade is climbing up the building day by day, and you can begin to see the real shape of this building (not to mention a nice slanted roof).

Looking directly at the front of the project from 16th Street, you can see the nice seamless glass wall, matching its neighbor building as well as some other buildings in the area. On the other side, facing 16th Street directly, it looks like there will be a complete wall of glass as the facade. Neat!

 

On to the back side, you have a nice slanted rooftop and a great looking backdrop to the rail tracks. On the right, you can see how DaVita and its neighbor (1900 16th Street) have very similar facades. Having the two buildings so close together prevents any clash and is easy on the eyes. The slanted roof also gives Denver something it hasn’t seen much in the past.

 

It’s always nice seeing other construction projects around you when taking pictures. From the Millennium Bridge, you can see 2020 Lawrence beginning to poke out. That’s its red crane and a concrete pump. Soon you will be able to see this project from the bridge!


Denver Union Station Update #93: A 2011 Retrospective

In keeping with Ken’s tradition of looking back over the previous year of Denver projects, he and I thought you might enjoy a retrospective of the Union Station project.

If you are new to this website or new to Denver, you need to know that there is a new bus terminal behind Union Station. Really! It’s there. And here’s the story of it so far.

The two photos below are from Update #48 on January 7, 2011. As you can see in the first one, much work on phase one of the bus terminal had been accomplished in 2010: the giant hole was excavated; the four-foot thick floor was laid; the walls were built; and the roof beams were being installed. Notice that three cranes were at work.

 

In the second photo above, the canopy over the light rail platform was completed, and finishing touches were in progress on the mall shuttle canopy.

So that’s the way it was at the beginning of 2011. The day after returning from a long road trip in late February, I met with Hunter Sydnor at Kiewit’s office to get an update on seven weeks of progress. And there was plenty for us to talk about.

By the end of February, the bus terminal roof was nearly complete (first photo below), the vertical walls of the skylights had been built (second photo), and the foundations for the three air inlet/outlet towers were in place.

 

Still in February, finishing touches were being made on the light rail tracks, and the Amtrak station had  moved to its temporary quarters on February 3.

 

By mid-March, the bus terminal was water-tight so the dewatering system was dismantled and the filtration system was hauled away. Work on the light rail overhead catenary system was underway (see photo below) and backfilling behind the bus terminal walls was nearly finished.

 

In Update #58 on April 10, I showed the following contrasting photos of the scene immediately behind Union Station. The span of time between the two photos was a mere five weeks. The tracks were gone, and the Amtrak passenger platforms had been demolished. However, the mall shuttle platforms remained for a while longer.

 

Backfilling on the roof of the bus terminal began in early April. In the photo below, you can see early backfilling and the waterproofing material being applied to the roof.

On April 26, excavation of the second half of the bus terminal began. It wasn’t long before the mail and baggage tunnels were revealed for the first time in many decades. Here’s a photo of the mail tunnel near 16th Street.

On April 28, I got my first tour inside of the bus terminal and wrote about it in Update #61. I remember being struck by the immensity of the space.

Moving along, the month of May saw the construction of streets. The mall shuttle loop was being built and Chestnut Place was being rebuilt, crossing over the bus terminal roof.

If there is a sad part of this story, it’s the loss of the beloved, historic passenger tunnel. In several posts throughout 2011, I gushed about the historic significance of that tunnel and my personal attachment to it: my Dad’s passing through that tunnel upon his return from the war in the Pacific in 1946 en route home to Medina, New York, to see his four month old son (me) for the first time. Here’s a photo of the beginning of the tunnel’s demolition in May 2011.

I like the following photo. It’s a wide shot of the area behind the station at mid-year. Phase 2 excavation was well underway; the mall shuttle station was still in operation, all three of the tunnels were gone; Wewatta Street was still open.

It’s exciting when a project gets to the finishing-touches stage. Lots of highly visible stuff happens. In mid-July, the Chestnut Pavilion started to take shape, and the new light rail station passenger platforms were completed (first photo below). Also, streets were completed, and the three air intake/outlet towers were built. The second photo is a good reminder of the appearance of the towers since they have been wrapped in blue plastic for the past several months. They are due to be unwrapped soon.

 

The Central Platte Valley Light Rail Line was shut down on July 22 in preparation of connecting the tracks at the new light rail station to the main line. Also in late-July, 16th Street and the light rail tracks embedded in it were torn up.

 

The lights were turned on for the first time on August 2 at the newly completed light rail station. This is another of my favorite shots.

The month of August was huge. Everything to do with the new light rail station was coming together: tracks, lighting, sidewalks, signage, railings, even light rail tests rides. The place was ready for action.

 

Then it finally happened. The new light rail and mall shuttle stations opened on August 15, 2011. This photo is from 5:50 that morning. I think it was the arrival of the first train. A VIP train following a couple of hours later. Go to Update #82 to see several videos of the celebration.

The first photo below is the scene at 8:00AM on August 22. The second one is 2:00pm on August 25. Nuff said.

 

By mid-September,the Chestnut Pavilion canopy was finished, the tear-drop planters started to show up, and a new pile of dirt was growing.

After a delay of several weeks due to a water contamination problem that was difficult to remedy, phase two excavation resumed by late-October. At the same time, there was plenty of activity constructing the tear-drop planters near the new light rail station.

 

Phase two excavation was nearly complete in November. Work began and continued into December on foundations for the eight sets of tracks (commuter rail, Amtrak, and Ski Train) that will be place over the roof of the bus terminal immediately behind Union Station.

As most big construction projects near completion, they rise up to highly visible structures that can be admired from near or far.  Not so with the Union Station project; progress results in its disappearance. I can’t wait for that first bus ride from the shining, new terminal that is someplace underground.

At the end of almost every blog, I remind you to take a look at JobSiteVistor.com for a more thorough visual tour of the project. By now, I have posted hundreds of photos on that site. You may enjoy a complete tour as I have done while writing this year’s retrospective.


20th & Chestnut Project Approaches Groundbreaking

The Nichols Partnership‘s proposed grocery-anchored residential project in Downtown Denver’s Union Station district is on track for a March 1, 2012 groundbreaking.

Covering most of the block bounded by Chestnut Place, 20th Street, Wewatta Street, and 19th Street in the redevelopment area west of Union Station, the project will feature 55,000 square feet of retail (most of which will be a full-service national-chain grocer) and 312 rental apartments. Our last profile on the project was in April 2011, and since then the project has received its approvals from the city and is preparing for the start of construction.

Courtesy of the Nichols Partnership and the Mulhern Group, here are the latest and final renderings for the project. First, an axonometric view looking south at the corner of 20th and Chestnut:

Here’s a closer view of the same corner at 20th & Chestnut, with 20th Street on the left and Chestnut on the right:

Next, a perspective looking east at the corner of 19th & Chestnut, with Chestnut on the left and 19th Street on the right:

Finally, here’s a view looking north from near 19th and Wewatta, with 19th Street on the left. The grassy area on the right is the remaining portion of the block along Wewatta that will be developed in the future as a mid-rise tower:

Of course, the presence of the grocery store component of the project is big news for Downtown, but this development is also important for the way that it will begin to close in the gap between Riverfront Park and LoDo, as well as help connect the Prospect district with the Union Station area. It will be the first project to get underway in the area immediately west of Union Station and north of 16th Street, but it certainly won’t be the last. We’re on the cusp of a once-in-a-lifetime building boom around Union Station.

The Nichols Partnership’s 20th & Chestnut project will open in December, 2013.


Denver Union Station Update #92

Work on the project has concentrated on one relatively small space for the past several weeks. Gone for now are the days of having activity scattered throughout the project area: light rail tracks, new stations, new streets, new sidewalks, etc. All of those have been completed. Now the work is confined to excavating the second portion of the bus terminal and building infrastructure inside the first portion.  Below is a photo from earlier this week that I took through a window inside Union Station.

It appears that the excavation work is nearly completed. Foundations are being built for the second set of elevators, stairs, escalators, and for the train tracks that will lay on the roof of the bus station. In the center of the background of the photo just below and slightly to the left of Glass House, notice the large sheet of vertical plastic with bright lights behind. You are looking at the lights inside of the first portion of the bus terminal. The vertical steel beams in the foreground support the shoring wall that is immediately behind Union Station.

It’s difficult to get a perspective from the photo. I’ll try to help. The scale of the hole is similar the first section: the same dept (about 28 feet), the same width, but a little shorter. I’m guessing that the first section is about 75% of the total length of the bus terminal.