Denver’s new skyscraper in the making has reached another milestone. The concrete parking structure for 1144 Fifteenth has topped out and steel, for the first floor of offices, is starting to go up!

As of today, four steel beams have started framing the 13th floor. If you are having a hard time seeing it, the steel beams are on the left side of the first photo.

2016-10-25_1144fifteenth-02 2016-10-25_1144fifteenth-03

Heading to the street level, we can see that the glass facade is quickly progressing on the northwest side of the tower.

2016-10-25_1144fifteenth-04 2016-10-25_1144fifteenth-05

As a bonus, here is a photo taken by one of our awesome DenverInfill readers.

2016-10-25_1144fifteenth-01

Steel structure almost always rises faster than concrete, so we should see brisk vertical progress moving forward. How exciting!