Back in July, we announced that the Modera River North Arts project broke ground. As a refresher, this project will rise five stories and add 183 units to the River North neighborhood.

Over the past four months, excavation has taken place and is now complete. The foundation for the underground parking garage is now going up along with the first level. Two self-erecting cranes also sit on the site. Here are two site photos from last week.

2016-11-18_moderarinoarts-03 2016-11-18_moderarinoarts-02

Once the underground structure is complete, the wood framing should go up fairly quick. We will check back when the framing begins.