Back in July, we announced a new 8-story, 164-unit apartment building that was replacing a single story parking garage in the Cherry Creek neighborhood. Since the announcement, construction is now underway for Alexan Cherry Creek.

Excavation for this project is complete and work for the foundation and underground parking structure has begun. Judging by the size of the hole, there will be three levels of underground parking which will be shared with residents and the offices around this project.

2016_01_24_AlexanCherryCreek-02 2016_01_24_AlexanCherryCreek-01

There is also a top-slewing tower crane on site that will be there for most of 2016.

2016_01_24_AlexanCherryCreek-03

A lot of work still has to be done to get this project out of the hole. Once it is out of the ground, we will swing back around for its next update!