Just over the tracks from our previous River North Roundup, the North quadrant has a lot of construction activity taking place. While the East quadrant still takes the reign for the tallest and densest projects under construction, the North quadrant is catching up and has some great projects that have either kicked off or are in the works.

UNDER CONSTRUCTION

Flora. Back in November, we reported that construction had kicked off for Flora, with excavation underway. Present-day, a tower crane has been erected on the project site, with the first vertical columns are going up above the street level.

Project Description Developer Architect Contractor
12 Stories | 92 apt homes | 7,500 sf office | 7,900 sf retail | 102 (v) parking
Belay Development Studio Completiva
Swinerton

The Current. This new office building at 36th and Delgany Street is making swift vertical progress. The Current is halfway up with six floors to go until topping out.

Project Description Developer Architect Contractor
12 Stories | 238,000 sf office | 388 (v) parking
Schnitzer West
Davis Partnership Swinerton

Vib Hotel RiNo. The Vib Hotel RiNo is nearing completion. Facade work is mostly complete, except for one last corner, still wrapped in scaffolding. While completion was expected in Q4 2021, work should be wrapping up in the coming months.

Project Description Developer Architect Contractor
8 Stories | 140 rooms | 4 (v) parking Best Western
Base4 White Construction Group

3901 Wynkoop. Since our last visit in November, excavation is now complete at 3901 Wynkoop, with a tower crane up at the project site. Forms for the core and first columns have also started to appear at the site.

Project Description Developer Architect Contractor
7 Stories | 408 apt homes | 13,000 sf retail | 428 (v) 213 (b) parking
Carmel Partners
Stantec Carmel Partners

PROPOSED

Vert Lofts. Demolition of the single-story warehouse at 36th and Wynkoop is now complete, with the site cleared to make way for the 16-story Vert Lofts project. Construction permits have been filed with the city however, no construction activity is taking place on the project site just yet. While this still sits in the “proposed” status, we are hopeful it will move to the “construction” status in the coming weeks.

Project Description Developer Architect Contractor
16 Stories | 175 apt homes | 149 (v) parking
RiNo Vertical Development
Studio 646 I-Kota

In addition, here are two renderings of Vert Lofts.

Cambria Hotel RiNo. Catty-corner from the Vib Hotel, another hotel may soon be underway at 36th Street and Brighton Boulevard. Currently, a fence is around the project site, with demolition underway for the existing buildings. Building permits have been filed with the city so once demolition is complete, there is a good chance the project will start shortly thereafter.

Project Description Developer Architect Contractor
8 Stories | 153 rooms | 29 (v) parking
HighSide Development Baskervill Brinkmann

Chestnut Lofts. A building permit has been issued for the triangular lot at 35th and Chestnut Street. Currently, a fence is around the project site with no signs of construction activity just yet.

Project Description Developer Architect Contractor
8 Stories | 49 affordable homes
Chestnut Lofts LLC
Studio Completiva Brinkmann

Hurley Place Phase 1. Building permits have been filed for the first phase of Hurley Place. While no construction activity is taking place just yet, this is an exciting development that will help connect the river to the neighborhood. The first phase brings two 12-story towers, adding a considerable amount of density towards the river along Chestnut Place.

Project Description Developer Architect Contractor
12 Stories x2 | 198 apt homes | 300k sq ft office | 21k sq ft retail | 700 (v) parking Menalto Development Semple Brown Swinerton

Giambrocco. A new concept plan for the Giambrocco site has been filed with the city. The project is still in the very early stages of development, with limited details available.

Project Description Developer Architect Contractor
16 Stories | 241 apt homes | 184 (v) parking
N/A KTGY N/A

3800 Brighton. A concept has been filed with the city for a new project at 38th and Brighton Boulevard, next door to the under-construction 3901 Wynkoop project. Currently, a surface parking lot sits on the project site.

Project Description Developer Architect Contractor
13 Stories | 366 apt homes | 2k sf retail | 385 (v) parking
Carmel Partners N/A N/A

RiNo Art Park. While this isn’t vertical development, it is worth mentioning that the RiNo Art Park is now open, including the Denver Public Library at ArtPark. This new park ties in seamlessly to the soon-to-be Arkins Promenade, adding an invaluable amenity to the neighborhood. Here are some photos of the park just before winter came last year.

That’s a wrap for this quadrant. It’s amazing to watch this area transform into a more dense, walk-able neighborhood.

Maps for projects mentioned in this post:

Flora

The Current

Vib Hotel RiNo

3901 Wynkoop

Vert Lofts

Cambria Hotel RiNo

Chestnut Lofts

Hurley Place Phase 1

Giambrocco

3800 Brighton

RiNo Art Park